28th Aug 2009
SGB Mastclimbers™ improve cladding productivity by 300%
SGB have equipped their mastclimbing work platforms with a unique custom-designed
monorail system, which is helping contractors speed up construction of a new Grade
A commercial development in the heart of Glasgow. 2 West Regent Street is a high-specification
10-storey mixed-use development comprising nine floors of office accommodation
above a ground floor comprising retail units. The client is Scottish developer
City Site Estates.
In order to achieve efficient progress on the construction programme, main contractor
Taylor Woodrow needed to find an external access system that would allow the rapid
installation of the building’s glass curtain-walling façade, without monopolising
the site’s tower crane.
The solution was found in the form of nine SGB Mastclimbers™, five of which have
been specially modified with a custom-made monorail system designed to lift and
position the glass panels against the building’s 50m high façade. “It was important
that the handling system for the cladding panels did not take up valuable hook-time
from the site’s tower crane, which is used for all other materials handling on
site”, explains SGB Operations Supervisor Colin Farquharson.
Working closely with Taylor Woodrow, SGB engineers expanded the existing capability
of the mast climbing work platforms and attached a horizontal monorail to the
top of each pair of mast towers. An electric winch, mounted on an underslung trolley
running along the monorail, carried the vacuum-lifting device that was used to
handle the glass panels.
“The monorail system effectively provided us with the equivalent of five cranes,
which has meant we could really speed up work on site” says Mike King, Project
Manager with Taylor Woodrow. “We were therefore able to maximise installation
of large glass units on multiple work faces which would otherwise have solely
relied on the tower crane thereby limiting the amount of labour we could use”
An additional advantage of the monorail system is that the low profile allows
it to continue operating at wind-speeds above that the tower crane cannot work.
Using the system saved approximately four weeks in the cladding schedule, estimates
Mr King. “The combination of the monorail with the mastclimbing work platform
helped us get early completion of the building envelope and improve productivity
by up to 300%”, he says. “The system itself is far quicker to install than traditional
scaffolding; in this case it took only about a week to install, whereas scaffolding
would have taken three or even four weeks”.
SGB started erecting the Mastclimbers™ in February 2009 and the cladding was
completed at the end of July.

